shui dian zhan zheng di yi min gong zuo guan li cheng xu jian jie
li you
..............
page:105
Safety Monitoring and Management during the Construction Supervision of Letan Project
zhao yan hui
..............
page:102-104
Research on the Dynamic Control Water Level in Flood Season in Yantan Power Station
chen biao ; mou cai rong ; chen xiao mei ; kong jian rong
..............
page:98-101,104
Comparison of Load Distribution Schemes in Frequency-changing Hoisting of the Gate
zuo shi hua ; huang jian
..............
page:94-97
Runaway Prevention of Bulb Unit
chen kang ming
..............
page:92-93
Overhual and Quality Control of Power Generator in Guigang Navigation Complex
meng huan chao
..............
page:89-91,97
Fuzzy-PID Control of Hydraulic Turbine Regulation System and its MATLAB Simulation
li ping ; cai wei you ; xiao zhi huai ; lu wan li
..............
page:85-88
High CFRDs Built in Narrow Valley
zhu zuo ; wang ji min
..............
page:81-84,88
Application of 3D Digital Cartoon to Tendering of Hydropower Projects
du tao ; luo yuan yao
..............
page:76-80
Non-linear Analysis on Contact Area Between Lock Chamber and Foundation Rock
xu you fei ; he jiang da ; liang zhao jiang ; wang kai yun ; li li ; chen zuo qiang
..............
page:71-75
A Probability-Weighing Approach for Calculating the Reliability of Structural System
huang han qiu ; wu zhang dun
..............
page:67-70
Critical Stable Sectional Area of the Downstream urge Tank with Linking Pipe
xia xiao juan ; song chang fu
..............
page:63-66
Study on the Anti-seepage Construction Technology for Dam with Concrete Impervious Facing
lao wu
..............
page:59-62
The Experiment Research on Dissipator of Diversion Pier with Low Ridge in Jinjitan Hydraulic Complex
sun gui kai ; xu wei zhang ; huang bing mei ; ning yu zhong
..............
page:54-58,75
Study on the Key Technical Issues in Construction of High RCC dam of Longtan Project
shi qing chun
..............
page:49-53,70
Construction Technology of Super Quality Concrete in Powerhouse of Letan Projec
huang ying kui ; huang ya xiong ; fu zhen hui
..............
page:43-48
Sprayed Concrete Construction with Polypropylene for the Underground Diversion System of Longtan Project
yang shi wen ; quan yan wen
..............
page:39-42
Control of Size Modulus of the Aggregate Plant of Letan Project
xu xi ye ; wei jian she ; deng ri nan
..............
page:36-38
Construction Technology Applied to the Curtain Grouting of Letan Hydropower Station,Bid I
tong sheng li ; zhou sheng cheng
..............
page:32-35
Experience on Anti-seepage Grouting for Dalongdong Reservoir
lao wu
..............
page:28-31
Overburden and Cracking Property of Shapai RCC Arch Dam
liang zhao jiang ; he jiang da ; xu you fei ; wang kai yun ; li li
..............
page:24-27,38
Grouting Construction of Dam Joints for the Three Gorges Project in Phase 2
yang xue xiang ; yu chang mao ; li yan
..............
page:19-23
Study on Some Key Factors in Design of Pre-stressed Pier
yang xiao hong ; hu qing yi
..............
page:14-18
Calculation Model of Lock Chamber Wall Based on FEM
wang kai yun ; he jiang da ; liang zhao jiang ; xu you fei
..............
page:9-13
On Seepage Property and Seepage Control of RCC Dam
zhu yue ming ; yuan cui ping ; qian min ; chu xiao zuo
..............
page:4-8
Design and Construction of River Closure for Longtan Hydropower Projec
song yi nong ; zhou jie ; li yong gang
..............
page:1-3,8