Journal of Railway Science and Engineering
1672-7029
2010 Issue 2
Prefabricating technology of double line whole-span simply supported box girder in Wuguang high speed railway
JIA Wei-hua
..............
page:74-78
Analysis of high-speed railway settlement observation data processing
WU Da-yong;YANG Yu-peng;HU Xiao-jun
..............
page:89-92
Filler experiment and subgrad filling technology of argillaceous siltstone for high speed railway
TIAN Da-peng
..............
page:31-37
Vacuum mud-jack technology of prestressed concrete cast-in-place beam in Wuguang high speed railway
WEN Chang-li
..............
page:66-69
Large volume concrete pile cap construction technology of Wang guanchong bridge in Wuguang passenger dedicated line
LIU Ming;CAO JUN;JIA Wei-hua
..............
page:83-88
Field filling technology of improved soil filler for pebbly sandstone
HU Xiao-jun
..............
page:102-109
Study of CRD method used in construction of Shizishi Tunnel
QIAO Jian-gang;GUAN Fa-zhi;GAO Chao;YUAN Wei
..............
page:98-101
Overline flexible protection construction technology on Wuguang high speed railway
WANG Ze-guo
..............
page:52-54
Application of track control network measure method in the building of Wuhan-Guangzhou passenger dedicated line
LANG Jian-ping;LIU Qian-wen;HU Xiao-jun
..............
page:16-19
Temperature control technology for composite concrete construction in summer
SHAO Chang-ging
..............
page:55-57
Application of mineral admixtures in high performance concrete
DONG Liang
..............
page:58-60
Small and medium continuous beams in high-speed railway of China
LIU Wen-shuo;DAI Gong-lian;HU Nan
..............
page:45-51
Non-strut formwork design and construction on bridge pier shaft of Wuhan-Guangzhou high-speed railway
CHEN Yong-xiang
..............
page:38-40
Technical features and construction strategy of Unit one of Section Ⅲ at Wuhan-Guangzhou high-speed railway
DING Shan-ye
..............
page:20-24
Cause analysis and construction technolog study of water-leakage of liner in Huangdengxian Tunnel
LIU Cheng-xian
..............
page:79-82
Settlement analysis for surcharge preloading subgrade in Wuhan-Guangzhou high-speed railway
GUO Zhi-guang;WEI Li-min;ZHOU Zhen-yong
..............
page:93-97
Strategies of procurement and distribution for distribution central of ceramic raw material
XIE Qing-chun;SHI Feng;QIN Jin;YAO Jia
..............
page:115-120
Static adjustment of CRTS Ⅰ double-block ballastless tract in Wuguang high speed railway
LANG Jian-ping
..............
page:1-4
Design of scaffolding system for whole box in Wuguang high speed railway girder construction
LANG Jian-ping;WANG Ze-guo;JIA Wei-hua
..............
page:5-9
Analysis of the application about integrated grounding system on ballstless track
LANG Jian-ping;SHAO Chang-qing;XU Na
..............
page:10-15
Prestressed construction technology of large span continue beam for high speed railway
XU Hua-xuan
..............
page:41-44
Investigation of improvement and reinforcement technology of silt ground in Jinshazhou tunnel
XU Mom-ei;YANG Ming;HU Heng-hu
..............
page:110-114
Construction technology bored pile in karst region of Wuhan-Guangzhou high-speed railway
CHANG Xiao-yi
..............
page:70-73
Construction technology of double-block ballastless track of Unit one of Section Ⅲ at Wuhan-Guangzhou high-speed railway
DING Shan-ye;YANG Yu-peng;GUAN Fa-zhi
..............
page:25-30
Construction monitoring technology of Wangguanchong bridge in Wuguang passenger dedicated line
ZHAO Yong-jun
..............
page:61-65
tou gao xu zhi
..............